Civil Package 3, Mechanical and Electrical (Installation): All foundation (tank and equipment), vacuum evaps plant, rotating kiln plant, recausticizing plant, bark gasifier plant, lime stone plant. MCC Room ((VE-RC & LK), Lime Slacker Building & Disk Filter Building, Power House Building, Power Generator, Auxiliary Diesel Generators (Power Generators System), Vacuum Evaporators, Rotary Kiln, Re-Causticizing Plant, Bark Gasifier Plant, Wood Handling Preparation, Chemical Plant, Piping Underground.

The package includes:

  • Tissue Machine Installation
  • Tank Fabrication, Erection & Testing
  • Piping Fabrication, Erection & Testing
  • Ducting Fabrication, Erection & Testing
  • Mechanical Installation of pumps, agitators, disc filters, refiners, deflakers, wash press, compressor, screens and other auxiliary equipment
  • Mechanical Installation of Rewinders & Roll Handling system
  • Fire Hydrant and Sprinkler System